Investors and lenders
A development-stage project, presented the way diligence requires.
This page sets out the investment case, the indicative scale of capital, the intended financing structure and the items that remain open.
Investment case
Why green ammonia in India, and why now.
Policy-backed demand
Under the National Green Hydrogen Mission, the Solar Energy Corporation of India has tendered 724,000 tonnes a year of green ammonia for fertiliser units, and supply agreements covering 670,000 tonnes a year were exchanged in March 2026.
Long-tenor contract model
The contract shape that has cleared in India is a fixed rupee price for 10 years with a government intermediary, supported by a production incentive in the first three years of supply.
Import substitution
India's non-urea fertiliser sector uses about 2.3 million tonnes of imported grey ammonia a year. Domestic green supply reduces exposure to gas prices and foreign exchange.
Dedicated debt products
IREDA publishes financing norms for green hydrogen and its derivatives, with lending of up to 70% of project cost and repayment periods of up to 20 years.
Proven technology
Alkaline electrolysis, Haber-Bosch synthesis and refrigerated storage are established, with multiple qualified suppliers for each package.
Export optionality
Ammonia is a traded commodity with existing shipping. The plant's storage is designed around standard export parcels, keeping overseas markets open alongside domestic buyers.
Sources: Ministry of New and Renewable Energy; Solar Energy Corporation of India; Council on Energy, Environment and Water (2025); IREDA financing norms (2026). Existing tender volumes are contracted to other parties and are cited as market evidence, not as this project's offtake.
Indicative scale
Project at a glance.
Figures are from our pre-feasibility model for the lead case: firm purchased hydropower and a 25,000 tonne export parcel. They are benchmark-based screening estimates, not supplier quotations.
The full model, with assumptions, sensitivities and automated tests, is available to qualified parties under a confidentiality agreement.
| Saleable green ammonia | ~552,000 t / year |
|---|---|
| Green hydrogen feed | 100,000 t / year |
| Electrolysis capacity | ~720 MW |
| Electricity demand | ~6.2 TWh / year |
| Indicative installed cost | ~₹17,400 crore |
| Stage | Pre-feasibility complete |
Installed cost covers the plant, ammonia storage and origin loading interface in the lead case. It excludes land, ocean freight, destination costs, taxes and duties, and financing costs, and will be replaced by quoted estimates at feasibility stage.
Financing structure
Intended structure: a sponsor-backed project company.
Shailka Systems acts as originator and developer. The project is intended to be held in a dedicated special purpose vehicle, with construction equity led by a financially capable strategic sponsor and long-term debt from Indian and international lenders.
Status. This is the structure we are working towards. No equity commitment, loan sanction or term sheet is in place.
Indicative capital mix
Based on IREDA's published norms for green hydrogen and derivatives: maximum 70% of project cost, minimum 30% promoter contribution.
Funding routes under evaluation
- IREDA term lending for green hydrogen and derivatives
- Domestic bank consortium project finance
- Development finance institutions
- Export credit linked to imported equipment
- Strategic and infrastructure equity partners
- National Green Hydrogen Mission production incentives, where eligible
Risks and open items
What must be true before investment.
We keep a live register of unresolved items. These are the principal ones, with the route to closing each.
| Area | Open item | Route to closure | Status |
|---|---|---|---|
| Offtake and price | No offtake is contracted. Green ammonia costs more to produce than grey ammonia, and project returns depend on the contracted price, incentives and delivered power tariff. | Government tenders, bilateral fertiliser and export contracts; buyer credit and acceptance terms. | Open |
| Power | No power purchase agreement. Tariff, firmness and hourly profile are modelled assumptions. | Term sheets with generators; multi-year hourly generation data; open-access charges confirmed. | Open |
| Site | No land, water, grid or terminal rights are held. | Allotment, water sanction and connectivity approval at a qualifying site. | Open |
| Technology and cost | Capital cost is benchmark-based. Yields and energy consumption are unguaranteed. | Competitive RFQs; licensor and EPC performance guarantees; FEED. | RFQs prepared |
| Certification | Green certification depends on the final power arrangement and the destination market's rules. | Certification pre-assessment against Indian and export-market schemes. | Open |
| Permitting and safety | Ammonia and hydrogen are hazardous; environmental clearance and safety approvals are required. | Environmental and social impact assessment; quantitative risk assessment; statutory approvals. | Planned |
| Sponsor and funding | Construction equity and debt are not committed. | Strategic sponsor selection; lender engagement after site, power and offtake are evidenced. | In progress |
Due diligence materials
A documented, source-traceable evidence base.
Every figure we use is tied to a dated source or a stated assumption. The development record is organised for technical, commercial and legal review and is shared with qualified parties under a confidentiality agreement.
Request data room access- Consolidated research dossier (580 pages) with source registers
- Economic model: assumptions, hourly dispatch, sensitivities and tests
- Design basis and RFQ basis for the ammonia train
- Electrolyser comparison: 22 manufacturer groups, 79 references
- Plant vendor matrix and RFQ question set
- Offtake assessment with domestic and international buyer records
- Site register, port readiness and ammonia shipping analysis
- Power sourcing, seasonal dispatch and carbon intensity assessment
- Incentive, subsidy and financing route registers
Important notice
Forward-looking statements and basis of information.
The information on this website is provided for general information about a project that is under development. It is not an offer to sell, or a solicitation of an offer to buy, any security or other financial instrument in any jurisdiction, and is not a prospectus, information memorandum or offer document.
Capacity, cost, energy and production figures are preliminary estimates from pre-feasibility studies dated November 2026. They rely on public benchmarks and stated assumptions rather than binding supplier quotations or guarantees, and may change materially. Statements about future development, financing, construction or operation are forward-looking and involve risks and uncertainties, including those summarised above.
References to government schemes, tenders, incentives and lender norms describe publicly available information as at the dates of our research. They do not imply that the project has applied for, been awarded or qualified for any of them. Recipients should make their own independent assessment and take their own professional advice.